The main building is made of brick, shot from the outside.

About the Plant

  • commissioning date: 14 Feb. 1901
  • sources of water taken in: the Sanka River
  • maximum output: 50 000 m3/24-hour
  • current production: 12 000 – 15 000 m3/24-hour
  • plant area: 45 ha (the Bielany Water Treatment Plant including the Kościuszko complex of tanks, the Tyniec and Las Wolski tanks)
  • disinfection technology: sodium hypochlorite produced from kitchen salt in electrolysers
  • number of consumers supplied: approx. 70 000 – 150 000